Pine Bluff High School | June 2026
Pine Bluff High School | June 2026
- The Career & Technical Education building is completed, and all MEP finals have been officially approved.
- New lounge furniture has been installed in the main classroom building and the cafeteria, bringing the spaces to life.
- Science lab casework installation is now underway.
- The Competition Arena hardwood floor is complete.
- Site concrete work continues to move forward, with only the ticket booth courtyard remaining.
- The History Wall laminate has been installed, adding another finished feature to the campus.
- Bleacher painting and cleaning are in progress, giving the stadium a refreshed appearance.
- Turf demolition has officially begun, marking a major step toward the new turf playing surface.
- All 4 new stadium light poles have been successfully installed and are standing tall.
St. Theresa Catholic School Breaks Ground on Renovation
St. Theresa Catholic School Breaks Ground Renovation
St. Theresa Catholic School proudly celebrated the groundbreaking of a transformational renovation project that will enhance learning opportunities and enrich the student experience for generations to come.
This exciting project will introduce several new and upgraded learning spaces, including:
– A new library and media center designed to inspire a love of reading and discovery.
– A dedicated art room where creativity can flourish.
– A modern Family & Consumer Science/STEM classroom that supports hands-on learning and innovation.
– A language and Spanish classroom that promotes global awareness and communication skills.
– Completely renovated restrooms for improved comfort and convenience.
The improvements extend beyond the classroom walls. The campus will also receive significant exterior upgrades, including:
– A new roof to protect and preserve our facilities.
– Updated storefront doors and windows that enhance both appearance and energy efficiency.
– Attractive new canopies to welcome students, families, and visitors.
In addition, a new parking lot will be constructed, adding 104 parking spaces to improve campus accessibility.
East Harding is honored to be a part of such an important project. Stay tuned for exciting updates!
620 West Third Office Building Completely Transformed
620 West Third Office Building Completely Transformed
Central Arkansas Water
Central Arkansas Water
Significant progress continues across CAW as multiple trades advance key milestones.
MEP rough-ins and interior framing remained in full swing, driving interior spaces closer to completion. A major project milestone was achieved with the delivery of structural steel and the start of steel erection for the south addition and stairwells, bringing the building’s expansion visibly to life.
Vertical progress continues on the North Elevator Tower, where CMU masonry installation is steadily taking shape. Outside the building, crews maintained momentum with ongoing exterior concrete work and retaining wall construction, further defining the site’s infrastructure.
We are so excited about the progress being made! Check back soon for more exciting updates.