Pine Bluff High School | July 2026
The finish line is in sight! Exciting progress continues as the stadium enters its final stages of construction!
– New turf is down on the field.
– Field painting is complete.
– New sports lighting poles are installed.
– The south parking lot off 11th Street has been freshly repaved.
– Ticket booths are now under construction.
– Topsoil is being placed around the site, with hydroseeding set to begin within the next two weeks.
Inside the campus, the momentum continues:
– The interior school courtyard is 100% complete, featuring new – AstroTurf, lighting, and finished concrete steps.
– Goals and netting have been installed in the gym.
– The kitchen is nearly finished, with crews wrapping up final utility connections and sink installations.
It’s incredible to see this project come together. Stay tuned—we’re getting closer to welcoming students, athletes, and the community into an amazing new facility!