Pine Bluff High School | June 2026
Exciting momentum continues across both the high school and stadium projects as we push toward the finish line.
- The Career & Technical Education building is completed, and all MEP finals have been officially approved.
- New lounge furniture has been installed in the main classroom building and the cafeteria, bringing the spaces to life.
- Science lab casework installation is now underway.
- The Competition Arena hardwood floor is complete.
- Site concrete work continues to move forward, with only the ticket booth courtyard remaining.
- The History Wall laminate has been installed, adding another finished feature to the campus.
Stadium Progress
- Bleacher painting and cleaning are in progress, giving the stadium a refreshed appearance.
- Turf demolition has officially begun, marking a major step toward the new turf playing surface.
- All 4 new stadium light poles have been successfully installed and are standing tall.
Every week brings visible progress and another step closer to delivering outstanding facilities for students, staff, and the community!